Input specification vs output specification
Traditional specifications are ‘input specifications’. They are prescriptive, that is, they describe in detail the products, materials and work (the inputs) required by a contract. Typically, the development of the solution required by the contract is complete and no (or little) further development is required by the supplier. The specification is considered to be a ‘closed specification’.
Prescriptive input specifications give the client certainty about the end product when making investment decisions, but place a greater burden on them to ensure the product has been thoroughly considered, developed and described. They tend to be used where a very specific end result required.
Output specifications define only the outcomes (or outputs) that are required by the contract, that is, what it will enable the client to do. They are open specifications that do not attempt to address how those outputs might be achieved. For example, an output specification might require the provision of a space for teaching 30 primary pupils, but it would not specify the nature of the space, the types of doors and windows etc. The standard for what is required might be defined, for example, by reference to performance targets.
It is argued that output specifications can get the best value from the supply team by allowing them to adopt innovative solutions to the client's requirements and reduce whole-life costs rather than simply developing the client's pre-conceived solutions at the lowest price.
For more information see: Output-based specification.
[edit] Related articles on Designing Buildings Wiki
- Briefing documents.
- Feasibility studies.
- Final specifications.
- Insulation specification.
- Outline specification.
- Output specification
- Output-based specification.
- Performance specification.
- Prescriptive specification.
- Procurement.
- Service level specification.
- Specification.
- Tender documentation.
- Tender process.
Featured articles and news
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.