Fluctuations in construction contracts
Fluctuations provisions in construction contracts provide a mechanism for dealing with the effects of inflation, which on large projects lasting several years can be very significant. On smaller projects, the contractor will be expected to take inflation into account when calculating their price (a firm price). On larger projects, the contractor may be asked to tender based on current prices (prices at an agreed base date) and then the contract makes provisions for the contractor to be reimbursed for price changes to specified items over the duration of the project (a fluctuating price).
Fluctuation clauses in contracts may allow for:
- Changes in taxation.
- Changes in the cost of labour, transport and materials (sometimes referred to as 'escalation').
- Increases in head office or administrative costs.
Generally the contractor is not entitled to fluctuations after the completion date.
The amount of fluctuations may be calculated from nationally published price indices rather than calculating actual cost increases which could be very time consuming. Provisions vary from contract to contract, and even within contracts there may be several options for fluctuations.
JCT for example has three options:
- Option A: contribution, levy and tax fluctuations.
- Option B: labour and materials cost and tax fluctuations.
- Option C: formula adjustment.
Option C is based on the Price Adjustment Formula Indices (PAFI), and are maintained by BCIS, and the specification of a base month against which changes are to be calculated.
Payment calculations might for exampled be based on a project programme for activity and a payment chart against the programme resulting in a cash flow projection. Quarterly percentage assessments of inflation are then added to the projected figures allowing for price fluctuation.
If industry negotiated labour rates are known in advance or a particular commodity such as steel is subject to spiralling price rises, additional allowances may come into play.
See also: Inflation in the construction industry.
[edit] Related articles on Designing Buildings
- Base date.
- Cash flow estimate.
- CLC urges inclusion of fluctuations provisions in contracts.
- Construction inflation.
- Contract conditions.
- Contract sum.
- Escalation.
- Inflation.
- Procurement route.
- Tender.
- Tender inflation.
[edit] External references
- Guide to DB05, Sarah Lupton, p101.
- Architect's Legal Handbook, Ninth edition, Anthony Speaight and Gregory Stone, Architectural Press 2010, Page 200.
- Estimating and Tendering for Construction Work, Martin Brook, Third Edition, Elsevier Butterworth Heinemann, 2004, P185. Available from RICS books.
- RICS professional standards and guidance, UK Fluctuations 1st edition, August 2016.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.