Escalation
Civil Engineering Procedure, 7th edition, published by the Institution of Civil Engineers (ICE) defines ‘escalation’ as an: 'Increases (or decreases) in the costs of labour or materials due to inflation (or recession and deflation).'
Some contracts make provisions for contract price adjustment to allow for the effects of escalation based on data about changes in the cost of commodities, labour, fuel and so on. Such allowances might be referred to as ‘fluctuations’ as there is a fluctuating price in the contract (although fluctuations generally also allow for changes in taxation and increases in head office or administrative costs).
On smaller projects of a short duration, the contractor may be expected to have taken the effects of escalation into account when calculating their price, and they may be able to hold sub-contractors and suppliers to agreed prices for the duration of the contract.
On larger projects, typically lasting more than a year, the contractor may be asked to tender based on prices at an agreed base date, and then the contract makes provisions for escalation to specified items over the duration of the project, such as fuel, steel and so on.
Determining the actual amount of escalation for each item would be very time consuming, and so calculations are generally based on agreed indices, such as public records, JCT bulletins and so on.
Escalation can be caused by issues such as:
- An overheating construction industry.
- Natural disasters.
- Exchange rate changes.
- Changes to regulations.
- Supply problems.
- Labour shortages.
- Inflation in the wider economy, such as fuel price increases or wage increases.
- Global economic conditions.
Escalation clauses put the client at risk, as the final price is not known when the contract is agreed. It is sensible therefore for clients to forecast likely escalation during the course of the project and to make allowances for this, with a contingency provision.
Significant escalation which has not been allowed for can result in the scope of projects being reduced, and can even bring projects to a halt.
However, if there were no escalation provisions, the contractor would have to bear all the risk of price changes, and this would be reflected in their tender.
NB ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines escalation as: ‘A positive or negative factor or rate reflecting an estimate of differential increase/decrease in the general price level for a particular commodity, or group of commodities, or resources (ISO 15686-5).’
[edit] Related articles on Designing Buildings
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.