Earned value for construction contracts
Earned value analysis (EVA), also known as earned value management (EVM), is a technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.
Typically, EVA is carried out for each of the packages that make up the project. Actual outputs are measured against planned outputs (often on a weekly basis) using the units that individual companies use to price and measure work.
This provides an opportunity to investigate discrepancies and take remedial action where necessary. It also provides a fairly accurate insight into the financial wellbeing of package contractors and provides early warning of a shortage of resources or of an inefficient use of resources.
The key is to measure actual resource against planned resource using the production units by which estimates have been produced in order to price a tender. This can be:
- Hours worked per week.
- Number of workers per week.
- Volume of say, concrete per week per person.
- Units fixed per week per person.
These items can be plotted weekly to alert the user to trends and allow them to investigate causes. Furthermore, it provides an overall general picture of labour productivity for each monitored operation.
Carrying out this sort of analysis requires that project planning is broken down into packages and that tender documentation is drafted to require contractors to supply the information required.
[edit] Related articles on Designing Buildings Wiki
- Benchmarking.
- Contractor.
- Cost monitoring.
- Cost performance index (CPI).
- Identifying the causes of trends in construction labour productivity.
- Key performance indicators.
- Programme consultant.
- Progress of construction works.
- Schedule performance index (SPI).
- Sub-contractor.
- Tender.
- Tender documentation.
[edit] External references
Featured articles and news
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.