Time and material contract (T&M)
In the United States, a time and material contract (T&M) is a type of construction contract that commits the client to pay the contractor based upon the time spent on the works, the materials used, as well as a mark-up for profit. In the UK, this type of contract is known as a cost reimbursable contract or cost plus.
This differs from a fixed price contract which commits the client to pay the contractor a lump sum fee for fulfilling the contract regardless of the amount on labour, materials, and so on used. A T&M contract is typically used on projects where it is difficult to describe the extent of the works required accurately, or where specifications and requirements are likely to change as the project progresses.
The main items that can be included in a T&M contract are:
- Labour rates: The amount that will be charged for the workforce, which may also include insurance, taxes, and so on.
- Material mark-up: It is usual for the client to be charged the retail price for materials and for a mark-up to be added by the contractor if they have a pre-agreed wholesale price with the supplier.
- Not-to-exceed: A guaranteed maximum price which places an upper limit on what the client can be charged by the contractor.
The advantages of using a T&M contract include:
- It provides the client with cost transparency and allows them to verify invoices and timesheets to ensure the costs are correct.
- It allows for greater flexibility in the extent of the works required.
- It allows works to progress even when there is no definitive plan for how it will be completed.
- It saves time in the initial estimating process which otherwise has to be done to a much higher level of detail and accuracy.
- Although there is generally a limit on their profit, the contractor can proceed knowing they are going to recover expenses with some profit, and so they can avoiding cost-cutting.
The disadvantages of using a T&M contract include:
- It can prove more risky for the client to proceed without a clear understanding of the final cost.
- It can increase the likelihood of disputes arising.
- Errors or inaccurate estimates can leave them with a low profit that may not be deemed worthwhile.
- It can necessitate more involvement from the client to ensure the contractor is motivated to progressing the works on time and within budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.