Structural engineers' fees
Fees are generally payments to consultants to cover work they have undertaken for clients under the terms of an agreement. They are generally paid in instalments, either on regular dates or at pre-agreed stages of completed work.
Structural engineers fees may be calcuated based on time charges, as a fixed lump sum or as a percentage of the overall project cost. Fees are entirely dependent on the nature of the project and the circumstances of the appointment. Large new-build projects may attract lower percentage fees than small works to existing buildings (see table below), commercial work may attract lower fees than private residential work, and works to historic or listed buildings may attract higher fees.
The examples given below are indicative only and apply mainly to small projects. Fee calculation may be based on:
- Charging a lump sum, particularly for small projects (eg £1,000 for a standard domestic extension, plus extra for structural details or special foundations; or £750 for a loft conversion inclusive of calculations and structural details);
- Flat-rate fees: site visits (eg starting at £150 per visit); design of steel beams and bearing details (eg, £75 for a single beam and £50 for each beam thereafter); masonry check (eg £100); goal-post frame (eg £200 - £300); and steel connections (eg £50 per connection).
- Hourly or daily rates (eg £80-£100/hour; £400-£500 per half day, etc);
- A percentage of the project’s total cost (see table below).
The fee percentage will depend on the size of the project (in project cost terms). The following table gives the fees a structural engineer might charge (at 2013 prices) for work undertaken on commercial office developments in London of varying costs.
Construction cost (excl. contingencies and VAT) | Under £1.5m | £1.5m - £3m | £3m - £10m | £10m - £25m | £25m –£50m | £50m+ |
Struct'al engineer % and actual fee |
2% £30k max |
2% £30k – £60k |
1.8% £54k– £180k |
1.5% £150k – £375k |
1% £250k – £500k |
1% £500k+ |
Other things that might affect the fees charged include:
- Type and complexity of project (eg hospital v industrial shed);
- Scope of services. For example, full design and site inspection will attract a higher fee than a preliminary design that is then developed by the contractor;
- Anticipated repeat and/or bespoke elements of the design;
- Location of site and other consultant practices;
- Reputation of practice. For example, an accomplished engineering firm may charge more than one that is newly qualified;
- Client organisation and track record. This may affect how much support is required and the risk perceived by the engineers;
- Conditions of engagement. For example, the requirement for collateral warranties and partnering arrangements;
- Anticipated programme and resources required.
- Economic climate. Fees may be lower during recessions and higher during booms;
- Consultant workload, and
- Assessment of the competencies of other consultants.
When agreeing fees, it is important to be clear exactly what services are being provided, for example, do the fees include travel, printing costs, outline and detailed planning applications and so on. For more information see: Scope of services.
Professional institutes used to publish recommended fee scales expressed as a percentage of construction costs for a range of different building types. However, legislation aimed at preventing anti-competitive behaviour forced the institutes to abolish these scales, leaving little guidance for clients about what is normal.
Consequently, bidding for consultancy work has become a free-for-all in a highly competitive market. Some commentators argue that this has driven down fees, however, it may also have driven down standards and led to much design work being transferred from consultants to specialist contractors and suppliers who include design costs in their building agreements.
It is important therefore to obtain several quotes for fees, to be clear what is being provided and to be wary of just assuming the lowest quote provides the best value.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Architects fees.
- Base date.
- Charge-out rate.
- Compensation.
- Consideration.
- Construction organisations and strategy.
- Consultant team.
- Contractual obligation.
- Design team.
- Disbursement.
- Hourly rate.
- Invoice.
- Letter of appointment.
- Planning fees.
- Quantity surveyor’s fees.
- Rates.
- Schedule of services.
- Scope of services.
- Sub-consultant.
- Winning work.
Featured articles and news
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Tackling the lack of knowledge or confidence in heat pumps
The CICV Green Home Festival part of the Edinburgh Fringe.
Home improvements swapped for green energy upgrades
As applications down since and desire to reduce bills up.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
The Use of Natural Insulation Materials in Retrofit
New paper from STBA with support from SDF.
National Retrofit Hub in partnership with InstallerSHOW.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Biodiversity and the built environment digital series
The nature of building, with CIOB and CWP.
A call for prevention and sensitive re-use.
Risks to the long-term effectiveness of the BNG scheme
National Audit Office publish review of Biodiversity Net Gain.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
Comments
It would be nice if you could update the table to show a more realistic (current for 2021) percentage of fee.
These numbers are quite a way off what the market is currently.
This is a WIki site - if you have better information, please click 'Edit this article' and add it.