Self-build home: Confirm appointment of the design and build contractor to construct the home
NB Where a single-stage procurement route has been followed, and the contractor’s initial appointment was for both design and construction, the contract sum for the construction of the home will already have been agreed.
Ideally, when the the design and build contractor's appointment to construct the home is confirmed, negotiation is a mathematical exercise following the pricing criteria agreed in the first-stage when the contractor was appointed to design the home.
The first-stage appointment might have been made on the basis of a bespoke agreement, a consultancy agreement or a pre-construction services agreement (PCSA), with an appendix setting out the tender items to be applied to the construction contract, with a clause that made it clear there is no obligation to proceed to the construction contract, and in such circumstances the pre-construction fee would be full and final settlement of the contractor's costs.
However, there are likely to be items not anticipated in the first stage, for which negotiations will be necessary.
Negotiating at this point is difficult because the contractor is ‘embedded’ in the project and there is little threat from competition. This can mean that tender prices for the second stage of two-stage contracts are higher than traditional contracts, which are subject to full competition. However, there tend to be fewer variations and fewer claims; as the contractor has a longer period of familiarity with the project and a better-developed relationship with the self builder.
Ideally there will be some means of securing an alternative bid if negotiations with the contractor fail, albeit this is likely to result in delays and difficulties in attributing design liability.
Featured articles and news
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.