Redevelopment lease renewals
A recent case decided by the High Court will (if not overturned on appeal) have potential implications for some commercial tenants seeking renewals of their tenancies.
The case of S Franses Ltd. v The Cavendish Hotel (London) Ltd. involved a dealer in textiles that occupies areas in the ground and basement floors of London’s Cavendish Hotel and which wishes to renew its tenancy relying on the security given by the Landlord and Tenant Act 1954, which gives such tenants the right to renew their tenancies except in certain circumstances.
One of the circumstances in which a renewal can be refused is if the landlord wishes to demolish or reconstruct the premises occupied by the tenant. The landlord (which runs the hotel) claimed that it did and it could not carry out the works it wishes to undertake without gaining possession of the tenanted premises.
What made this somewhat different from the norm was that it appeared that the landlord would not have wanted to carry out the work it used to justify the termination of the tenancy if the tenant had agreed willingly to vacate the building. The tenant claimed that the landlord’s motivation was purely to evict it and therefore the landlord should not be allowed to terminate the lease.
The High Court’s judgment was that there was one core issue: did the landlord really intend to carry out the work? That alone would decide the matter. The landlord’s motivation for doing the work was not in point.
The case isn’t quite over. The County Court has to decide on the extent to which the work specified might be able to be done leaving the tenant in place and also the timescale in which the work should be commenced.
However, it is quite feasible that landlords seeking to remove protected commercial tenants may, if the premises offer a financially suitable redevelopment opportunity, use the works primarily as a device to remove an unwanted tenant.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.