Punch list
A punch list (also known as a snagging list) is a document that is prepared close to the end of a construction project and issued by the appropriate certifying authority (typically, the architect, contract administrator or employer’s agent). It lists any faults that are identified or works that do not conform to the specifications, which should be rectified prior to a certificate of practical completion being issued.
Generally, snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions (snages) in building works for the contractor to rectify.
For more information, see Snagging.
This differs from a work-to-complete list which is compiled by a contractor and issued to each subcontractor and their crews at, or near, completion - a list of the remaining items and any defective work that subcontractors are required to complete before leaving the site.
For more information, see Work-to-complete list.
The process of inspection and going through a punch list is usually performed close to the end, if not right at the end, of construction so that the work as a whole can be reviewed and checked. The list of items to be completed or corrected is compiled by the contractor and submitted to the employer’s agent or designer (usually the architect or engineer). Lists tend to be organised either by room or by trade.
Following this, the work is inspected by the agent (sometimes along with the contractor, subcontractor, owner, and any other relevant stakeholders) to determine whether the items on the list have been resolved. Traditionally, the list would be worked through and a hole punched in the margin to indicate that the particular item of work had been completed, hence the term ‘punch list’. Today, digital software is capable of producing virtual punch lists with applications that can be operated via mobile devices as well as more complex web and desktop varieties.
Typical examples of punch list items include: repairing broken windows, replacing missing roof tiles, repainting chipped paintwork, filling cracks, and so on.
Once the list of items has been completed according to the specifications in the contract, or a mutually agreed resolution has been decided upon for certain items, practical completion can be certified.
Following practical completion, there is generally a defects liability period, during which the contractor may be recalled to rectify defects which appear. This is not a chance to correct snagging items apparent at practical completion, If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.