Nominated supplier
In the construction industry, ‘supplier’ is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Typically, a contractor is able to purchase from their own choice of supplier, as long as they comply with the requirements set out in the specification. However, under certain circumstances, the client may wish to impose (or nominate) a particular supplier on the main contractor after the main contractor has been appointed.
The client may wish to use a particular supplier because:
- A particular product brand is required.
- The particular goods provided by the supplier are not widely available.
- There is an existing relationship with the supplier.
- Long delivery items are required where ordering is necessary before the appointment of a main contractor.
- Specialist design input is required in the early stages of design development.
- Complex or specialist industrial plant or equipment may be required, upon which the design will be based.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs. This allows the client to have direct separate negotiations with suppliers and feed their appointment into the contract after works by the main contractor have commenced.
A potential drawback of nominating a supplier is that the contractor is then not able to ‘shop around’ to obtain the best price or supplier. It is important therefore that suppliers are nominated with due consideration to their ability to supply in line with the project specification, programme and budget.
In addition, as the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for their failure to perform. However, as the supply contract is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated supplier to guarantee performance and indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
The complexity of this situation means that some forms of contract no longer include provision for the nomination, preferring to 'name' suppliers instead.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.