Construction progress report
Construction progress reports are prepared regularly (often monthly) by the contract administrator during the construction phase and issued to the client. They will generally be a summary of the reports received and discussions held at construction progress meetings.
Construction progress reports may be a combination of minutes of construction progress meetings and reports received during those meetings, with key issues highlighted in an accompanying cover note. Alternatively they may be a re-written version of that information prepared specifically to suit the client's requirements.
Construction progress reports might include:
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Weather reports.
- An assessment of any health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
Similar reports may be prepared on management contract projects in relation to works contractor progress.
[edit] Related articles on Designing Buildings Wiki
- Client.
- Construction progress meeting.
- Construction manager.
- Contractor.
- Contract administrator.
- Consultant team.
- Construction stage report.
- Earned value analysis.
- Employer's agent.
- Health and Safety.
- Management contractor.
- Progress of construction works.
- Project programme.
- Project manager.
- Project manager's report.
- Site meeting.
- Sub contractor.
- Warranties.
- Works contractor
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
Comments