Common refusals of extensions of time
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor should give written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.
Common reasons for the refusal of an application for extensions of time include:
- Where the contractor has underperformed, for example, as a result of insufficient workforce or failure to obtain plant, goods or service.
- When there has been poor, but not exceptionally adverse weather.
- When the evidence or other information presented to demonstrate that the contractor has suffered irrecoverable delays is insufficient.
- If an extension of time has already been given for that event.
- Where more than one event occurs at the same time. See Concurrent delay for more information.
- The event cited does not constitute a relevant event.
- An event does not constitute force majeure.
- An event does not constitute a specified peril.
- The contractor has not taken steps to mitigate the delay
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Change order.
- Compensation event.
- Contract administrator.
- Contract claims.
- Culpable delay.
- Delay damages.
- Extension of time.
- Extension of time - approval letter example.
- How to prepare a claim for an extension of time.
- Practical completion.
- Project programme.
- Time certainty.
- Time extension.
- Time Risk Allowance TRA.
- Variations.
Featured articles and news
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.