Building notice for building regulations approval
There are two ways of obtaining building regulations approval:
- A full plans application, and
- A building notice application.
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out. On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
A building notice application can be made with a simple application form, a site plan (if an extension is involved) and the appropriate fee (calculations may also be required for certain aspects depending on the complexity of the project). This means that work can begin very quickly, and need not necessarily involve design consultants.
However, a building notice application leaves the client at risk that completed works might not be approved, resulting in remedial costs. Clients should be certain that their builder is familiar with all the relevant regulations before deciding to follow this route. It is also worth considering that proceeding without a full set of agreed drawings is more likely to result in disputes.
Building control fees for a building notice may be more expensive than for a full plans application.
Building notices cannot be used:
- For building work to which the Regulatory Reform (Fire Safety) Order 2005 applies (generally commercial or industrial buildings).
- For building work close to, or over the top of rain water or foul drains.
- Where a new building will front onto a private street.
Inspections must be arranged in advance by giving notice to the building control inspector. Notice is likely to be required at:
- Commencement.
- Excavation for a foundation, before covering up.
- Foundations, before covering up.
- Damp proof course, before covering up.
- Concrete or other material laid over the site, before covering up.
- Drains.
- Structural timbers, steelwork or concrete, before covering up.
- Completion.
Other inspections may be deemed necessary by the inspector.
If the local authority is not given notice of work for inspection it may require that the work is opened up for inspection.
If the local authority believes the building work contravenes the building regulations, they may serve an enforcement notice requiring alteration or removal of the work that contravenes the regulations. It is not possible to ask for a determination (appeal) of an enforcement notice as there are no drawings upon which a determination could be made.
A building notice is valid for three years after which it will automatically lapse if the building work has not begun.
It is important to ensure that a completion certificate is sought as evidence that the works comply with the regulations. Under changes to the building regulations made in December 2012, Local Authorities must give completion certificates, they should not need to be requested.
NB: Full plans approvals are also subject to inspection during the course of the works, but as long as the work is carried out in accordance with the approved design, the risk of problems is very much lower than for a building notice application.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
London Build Fire and Security Expo
20-21 Nov and now with new Ambassador Programme..
The Scottish Building Safety Levy
Eight weeks of consultation closing on 18 November.
The grey, the brown and the golden rules of housing
shifting policies from the wild west of housing development.
Future proofing homes that are fit for purpose
Specification challenges and the role of plastic.
Thousands of new homes unlocked for brownfield sites
£68 million to 54 councils for neglected land into new homes.