Approved document S Infrastructure for the charging of electric vehicles
Approved Document S: infrastructure for charging electric vehicles, was published by the Department for Levelling Up, Housing and Communities on 15 December 2021. It provides technical guidance regarding the installation of charge points required by Part S of the Building Regulations.
Part S of the Building Regulations requires that certain buildings with associated parking must have access to electric vehicle charge points.
Very broadly, for new residential developments, a charge point is required for each parking space, with some exceptions. Where no associated parking spaces are provided, there is no requirement to instal a charge point.For non-residential developments with more than 10 parking spaces, one space must have access to a charge point, and cable routes must be provided to 20% of the other spaces. The charge points need to provide a minimum of 7kW to an untethered charger.
It sets an average cost cap of £3,600 for all work involved in installing a charge point. If the cost exceeds this, only the cable routes themselves need to be installed. Where the cost of is more than 7% of the total cost of a major renovation, there is no requirement to instal either electric vehicle charge points, or the cable routes if the cost of the cable routes is more than 7%.
Approved Document S applies to:
- New residential and non-residential buildings.
- Buildings undergoing a material change of use to dwellings.
- Residential and non-residential buildings undergoing major renovation.
- Mixed-use buildings that are either new, or undergoing major renovation.
Approved Document S came into effect on 15 June 2022, but does not apply to works where an initial notice was registered before 15 June 2022, provided the work starts before 15 June 2023.
[edit] Related articles on Designing Buildings
Featured articles and news
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
London Build Fire and Security Expo
20-21 Nov and now with new Ambassador Programme..
The Scottish Building Safety Levy
Eight weeks of consultation closing on 18 November.
The grey, the brown and the golden rules of housing
shifting policies from the wild west of housing development.
Future proofing homes that are fit for purpose
Specification challenges and the role of plastic.
Thousands of new homes unlocked for brownfield sites
£68 million to 54 councils for neglected land into new homes.